The stackable skips were filled with contaminated goods by the power station’s existing handling equipment, but then had to be moved into the storage area, where there was limited headroom above the top of the four storage channels, each of which then reached depths of 10m.
SCX Special Projects designed a handling system capable of securely collecting the skips, moving them into the containment area and precisely stacking them within these deep holes in the facility.